 Ground Prep Begins 5/7/08 |
 Removing Rail for Receiving Pit & Tunnel 6/16/08 |
No Image File Pouring base for Rail Pit 6/27/08 |
 View from above 8/5/08 |
 First big cement pour (500 yards in 7 hours) 8/18/08 |
 8/18/08 |
 Please stop the rain! 9/12/08 |
 Starting to take shape (9/17/08) |
 Roads and Warehouse are looking good (9/30/08) |